£260,000 worth of concrete repairs to the Grade 2 listed Goldthorpe Church in the village of Goldthorpe, Yorkshire, have been carried out by the UK’s leading specialist main contractor Concrete Repairs Ltd (CRL).

The rather unusual structure, believed to be the earliest ‘all-concrete’ constructed church, is a prominent physical and historic landmark in the area. It was built by local benefactor Lord Halifax at the outset of the First World War in the shortest possible time using the new ‘fast build’ material (then called ferroconcrete) designed to withstand local mining subsidence. The building’s roughcast finish, comprising pebbles up to 150mm, a variety of concrete mixes and textures, meant that the church was of national significance and the finished repairs needed to be sympathetic.

The new concrete was required to match the original yellow colour and its finished texture. Because of this, current concrete mix specifications were rejected, as were proprietary pre-blended materials. CRL reverted to 1960s style site mixing arrangements and it took more than 30 trial mixes to come up with the correct colour. Sourcing the various constituents also proved demanding. After breaking out some 20 cubic metres of the badly spalled concrete and reinstating it, the original exposed aggregate finish was achieved via the use of retarder-coated formwork and brushing out of the first few millimetres of soft laitence once the formwork was struck.

Supporting the church’s 200mm thick walls were 20 rectangular columns. When cut back each revealed that the reinforcement consisted only of a single 25mm diameter mild steel corner bar, without wrapping, nor continuity. Before repair, therefore, each required the installation of new reinforcement. In addition, the 19-metre high by 5-metre square bell tower was also found to be suffering major loss of section. Total demolition and rebuild was considered until CRL proposed strengthening with a 10-metre high steel frame before repair. This solution proved 60% cheaper than the demolition idea.

Other contractors claimed it was impossible to match the original finish and refused to tender for the project. CRL accepted the challenge and now it is difficult to tell the difference between the newly repaired and the old surfaces.

CRL NEWS ARCHIVE 2002:

November 2002
CRL SECURES HIGHWAYS AGENCY

October 2002
KEN DYKES JOINS CRL

September 2002
CRL CONQUERS THE CHALLENGE OF GOLDTHORPE CHURCH

August 2002
LICENSED TO RENOVATE

June 2002
FEMALE PILGRIM LABOURER FOR CRL

May 2002
TWO ICE BRIDGE AWARDS FOR CRL

April 2002
CRL OPERATIVES EXTRA-CURRICULA PASTIME GENERATES £1200 FOR CHILDREN'S WARD

February 2002
NEW REFURBISHMENT DIVISION LAUNCHED BY CRL

January 2002
TWO HUGE CAR PARKS WATERPROOFED BY CRL

CRL NEWS ARCHIVE:

2004 (CLICK HERE)

2003 (CLICK HERE)

2001 (CLICK HERE)

2000 (CLICK HERE)

1999 (CLICK HERE)