The refurbishment was delivered by CRL under challenging conditions, with the car park remaining fully operational on a 24/7 basis throughout the programme. This required careful sequencing, detailed planning and innovative engineering solutions to maintain access while undertaking extensive concrete repairs and upgrades. The reinforced concrete frame was surveyed, repaired and protected to enhance durability, address defects and improve overall appearance. Repairs were followed by the application of protective coatings designed to improve resistance to environmental exposure and ongoing wear from high traffic volumes.
A level-by-level approach was adopted, with each deck completed in a four-week cycle. Works progressed from initial cleaning and surface preparation through to detailed surveys, full electrical replacement, concrete repairs, decorations and deck coating application. To minimise programme duration, CRL selected high-quality, rapid-curing materials throughout. A Triflex PMMA DCS-C decking system was applied across approximately 21,000 square metres, incorporating a quartz anti-slip finish to enhance safety for both vehicles and pedestrians.
Each level was finished with a distinct colour scheme, clearly defining parking bays and extending into communal pedestrian areas. New pedestrian routes were introduced, alongside additional disabled and parent-and-child bays designed to meet DDA requirements. Externally, façade areas were repaired and coated in a Dolphin Blue colour scheme, improving visual appeal and encouraging footfall into the shopping centre.
Electrical works were delivered by CRL’s in-house specialist division, Equilux. A new low-output, wireless intelligent LED lighting system was designed, installed and commissioned, including full replacement of electrical components and containment. This integrated approach demonstrates CRL’s capability to deliver complex concrete repairs and structural repairs UK projects efficiently, combining civil engineering expertise with in-house building services to achieve cost certainty and programme reliability.